How to correctly calculate the consumption of cement per 1 cubic meter of mortar: for screed, masonry, plaster, foundation

Working with concrete requires knowing how to accurately calculate the amount of cement needed for screed, masonry, plaster, and foundation. Making accurate calculations guarantees that your mixture will perform, hold up, and have the appropriate strength for the job. Errors in calculations can result in expensive and time-consuming weak structures or excessive material waste.

Different cement, sand, and aggregate mixes are needed for different kinds of construction projects. For instance, the ratio of a concrete mix for a foundation will differ from that of masonry mortar. Finding the right ratios will help your project have the strength and consistency you want.

The main objective of screeds is to produce a level, smooth surface. To create a fine, workable mixture, this frequently calls for a higher sand to cement ratio. In contrast, more adhesive masonry mortar is required to firmly hold bricks or blocks together. To guarantee sufficient bonding strength, a careful balancing act between the cement and sand is necessary.

Plastering entails giving walls a textured or smooth finish. Here, the mixture must be fine and workable in order to spread readily and create a surface that will hold up after drying. Usually the strongest mix, the foundation mix requires more cement to support a building’s structural loads.

The first step in performing accurate calculations is to comprehend the particular needs of your project. This entails figuring out how much mortar is required, and then figuring out how much cement, sand, and aggregates are needed using standardized ratios. You can guarantee that your concrete mix is suitable for its intended use by adhering to these guidelines, which will improve the outcome and speed up the building process.

Type of Mortar Cement Consumption per 1 Cubic Meter
Screed 300-350 kg
Masonry 200-250 kg
Plaster 150-200 kg
Foundation 250-300 kg

Current SNiP or old-fashioned method

The amount of cement that may be required per cubic meter of mortar is answered fairly clearly by current regulations. Simultaneously, computations typically consider the ideal component volumes in addition to their properties, such as fraction, purity, humidity, density, and quality.

The conditions under which you intend to complete the work should be considered when examining the material consumption rates per cubic meter of concrete. As a result, SNiP assumes that concrete mixing and work are done in an environment with an average humidity and temperature of +23 degrees. Every part needs to be spotless and have a maximum humidity of 7%.

Cement should only be used when it is brand-new and fresh because storage can alter its density. Considering all of these details, experts suggest buying cement in quantities that are 10-15% greater than typical.

  • Cement grade M400 – for mortar M200 – 490 kilograms
  • Cement grade M500 – for mortar M200 – 410 kilograms
  • Cement grade M400 – for mortar M150 – 400 kilograms
  • Cement grade M500 – for mortar M150 – 330 kilograms

The following information can be found in the tables:

When preparing concrete, it is crucial to determine how much sand and crushed stone are required for every 1 m3 of solution, as these elements affect the monolith’s strength, dependability, durability, and other crucial properties.

The consumption of crushed stone and sand is displayed in the table:

Keep in mind that all calculations involving concrete preparation can be made using the total weight of a cubic meter of solution. However, that is untrue. It’s possible that the cement won’t add more volume to the concrete overall because it’s so finely ground and fills the spaces between the sand grains. In other words, the volume of solution (1 cubic meter) remains constant when 200 or 400 kg of cement are added.

Half of the mass (but not the volume) of cement is added to the mixture in water. It is important to consider the sand’s humidity; the wetter the sand, the less water will be required. It is best to add water in small amounts and monitor the consistency; the concrete will be ready for use once it reaches the necessary density.

Concrete should have the ideal consistency for work, regardless of brand. The standards state that the amount of settlement of the metal cone, which is lowered into the solution, determines the consistency.

However, using this method in construction conditions is generally not feasible. As a result, it is typically assessed visually: the solution’s density needs to be adequate for leveling, laying (pouring), and supporting formwork and seams without discomfort.

What does cement consumption depend on

The properties of the powder and the amount of cement needed in a cubic meter of mortar are determined by the technical requirements that the concrete must meet. The amounts can vary greatly between brands and types of concrete, as different amounts of cement, sand, gravel, and water are used in different amounts. Furthermore, the precise values differ based on a few variables.

  • The volume of fillers in the solution – the more sand and crushed stone, the more kg of cement, which acts as a binding component and holds the filler particles together. The optimal ratio of bulk mixtures is calculated based on the amount of cement.
  • The grade of cement used in mixing concrete – as the number increases, the strength of the structure/building being created increases. The grade of the final mixture is 1.5-2 times lower than the grade of cement, because gravel/crushed stone/slag and sand are also used in the composition.
  • The required grade of the solution that needs to be prepared – not only cement, but also concrete is divided into grades, each of which has certain characteristics and parameters. Only after determining the grade of concrete can you understand how much cement is needed per 1 cubic meter. So, for example, to obtain an M100 mixture using M500 cement, you need to mix part of the binder, 5.8 parts sand, 8.1 part crushed stone. But to obtain an M450 solution, the proportion looks like this: 1/1.4/2.9.
  • The density of cement also plays an important role. The indicator depends on the brand of cement, the average is 1300 kg/m3.

Therefore, the brand of cement (used in the batch) and the brand of concrete that must be obtained in the end directly affect the consumption of cement, sand, and crushed stone.

Types and brands of mixtures

There are two distinct indicators: concrete and cement grade. M400 cement can be used to produce concrete of various grades, depending on the volume of fillers and the kilogram of cement per 1 m3. Generally speaking, use cement grades 1.5–2 higher to prepare a solution of a particular brand.

Cement grade M100 is available under production conditions, but because of its low strength, it is rarely utilized. The most widely used cement brands are M400 and M500, which are utilized to prepare solutions M100–M600. For some jobs, other types are also pertinent.

The packaging bears a marking indicating the cement grade, denoted by the letter M and numbers. The material’s strength can be directly inferred from the grade. The strength of the solution is contingent upon the type and quantity of cement utilized. Working with concrete of a higher grade is more challenging, but the strength and other performance attributes will also increase.

  • M100 – implementation of the preparatory stage of various works (often concrete is laid in a thin layer on a sand cushion under the foundation)
  • M150 – foundation for small buildings, screed and pouring the base as a rough layer, concreting paths
  • M200 – pouring garden paths, foundations, blind areas, concrete screed in garages and residential premises
  • M250/M300 – creation of a monolithic foundation, stairs, fences, supports, medium-load floor slabs, blind areas
  • M350 – pouring critical structures (floor slabs, monolithic foundations, columns, crossbars, swimming pool bowls, etc.).d.)
  • M400 – construction of cash vaults, bridges, hydraulic structures, objects with special requirements
  • M450/M500/M550 – the same purposes as the M400 brand, also dams, embankments, metro
  • M600 – used in the construction of objects that require special resistance to aggressive factors, requiring maximum strength (reinforced concrete bridges, special-purpose structures, hydraulic structures, etc.d.).

Consumption rates for different solutions

The amount of cement in 1 m3 of solution can vary depending on the purpose of the concrete. Four tasks in modern construction are completed with concrete mortar: laying building blocks, pouring screeds, plastering, and pouring the foundation. It is assumed that a specific type of mortar with a specified volume of cement is prepared for each of the listed types of work.

The process of preparing a mixture for plastering or masonry results in the highest cement consumption per cubic meter of mortar. Using large fillers (gravel, crushed stone, slag) when pouring the foundation or screed helps to minimize the amount of cement used. The grade (which determines the properties of concrete and its primary characteristics) indicates the goal of the solution.

  • M100 – 170 kilograms of cement
  • M150 – 200 kilograms
  • M200 – 240 kilograms
  • M250 – 300 kilograms
  • M300 – 350 kilograms
  • M400 – 400 kilograms
  • M500 – 450 kilograms

For plaster

Three parts sand and one part cement are combined to make a standard plaster mortar. For every square meter of plaster grade M500, 1.6 kilograms of cement grade M400 and 1.4 kilograms of cement grade M400 are weighed, provided that the layer is no thicker than 12 millimeters. One can calculate the volume of mortar per cubic meter of masonry using the formula 1 m2 x 0.012 m = 0.012 m2 = 12 liters.

For masonry

At least 75 liters of M100 mortar are required for a square meter of brickwork that is one brick thick. M400 cement and sand have a 1:4 ratio. For bricklaying, 250 kg of cement are needed for every cubic meter of sand. The size of the building determines the total amount of cubic meters of mortar required.

A volume equal to half the cement’s weight is absorbed by water. Thus, if you use buckets to mix the mortar, you get this: Four buckets of sand, one bucket of M500 cement, and seven liters of water.

For the foundation

You have to do all of the calculations accurately in order to prepare a mortar for pouring the foundation. They typically use grades M100–M300 of mortar. M150 and M200 are appropriate for multi-story buildings, while M100 is strong enough for low-rise structures. The stronger the structure, the higher the grade. Use M300/M400 cement (1 part binder and 3 parts sand) or M500 cement (1 part binder and 5 sand) for mixing.

  • M50 (based on M400 cement) – 380 kilograms
  • M100 (based on M300 cement) – 214 kilograms
  • M200 (based on M400 cement) – 286 kilograms
  • M300 (based on M500 cement) – 382 kilograms

If the mixture is made in the following proportions: 1 part cement, 2-4 parts sand, and 3 parts crushed stone or gravel, then these calculations become pertinent.

For screed

One part cement and three parts sand are the proportions for mixing. You can demonstrate accurate calculation here. Thus, you need to apply a layer of 30 millimeters thick to cover a surface area of 3 by 4 square meters (12 turns).

  • Determining the required volume of concrete mortar: 12 m2 x 0.03 m = 0.36 m3.
  • Choosing the concrete grade – we take M200, prepare from M500 cement, of which 410 kilograms are needed.
  • Calculating the number of bags of cement: 410 kg x 0.36 m3 = 148 kg / 50 = 3 bags (almost).
  • How much sand is needed: 1600 kg/m3 (weight of a cubic meter of mixture) x 0.36 m3 (required amount of mixture) = 576 x 0.75 (proportion of sand in concrete) = 432 kilograms. A cubic meter of sand mortar will require about 1200 kilograms.

Ensuring the strength and durability of your construction project requires accurate cement calculations for various types of mortar. Knowing the proper proportions will ensure the best results while saving time and money when working on screeds, masonry, plaster, or foundations.

You’ll need a more fluid mixture for screeds, usually one part cement to three to five parts sand. This mixture creates a level, smooth surface that is perfect for flooring. In contrast, masonry work necessitates a stronger, more adhesive mixture—typically one part cement to three parts sand—to guarantee dependable and robust brick or block construction.

In plaster, the mixture is typically lighter, consisting of roughly 1 part cement to 4-6 parts sand. This produces an easy-to-apply, workable consistency that gives walls and ceilings a polished, clean look. In order to support the weight of the structure above, the mix used for foundations needs to be much stronger. One part cement to two parts sand and four parts gravel is a typical ratio that provides the required stability and robustness.

Gaining an understanding of these ratios and modifying them in accordance with the particular needs of your construction project will help you accomplish maximum performance and long-term results. You can make sure that your materials are used effectively and prevent waste and potential structural problems by taking the time to do accurate calculations.

In conclusion, every kind of mortar mix has unique requirements, and precise cement consumption calculations are essential for a job well done. Equipped with this understanding, you can tackle your tasks with assurance, knowing that you possess the appropriate combination for the task at hand.

Whether working on screed, masonry, plaster, or foundation, it is imperative to calculate the correct amount of cement for one cubic meter of mortar. The secret is to know the precise mix ratios needed for each kind of work, which can change depending on the level of strength and durability needed. Knowing the exact ratio of sand, cement, and other materials will help you save money and time while guaranteeing a sturdy, long-lasting outcome. This post will walk you through the easy procedures and calculations required to calculate the precise amount of cement your project will require.

Video on the topic

We purchase the required volume, or What is the cement consumption per cubic meter of mortar for screed, masonry, pieces.

Which aspect of concrete application are you most interested in?